Skip to main content

Marjan Increment Project - Package 1

Offshore - Jackets & Topsides
Marjan Increment Project - Package 1
2019

awarded

6

large topsides

10,000

employees at peak

Scope
EPCI
Location
Offshore Saudi Arabia
Highlights
  • Single largest offshore EPCI project awarded by Saudi Aramco in Dodsal Group’s history.  
  • Landmark project where Dodsal Group transitions from its legacy conventional float over methodology to DP (Dynamic Positioning) for all six large topsides. 
  • Project execution spread over five fabrication yards.

The project comprises an entire offshore GOSP complex including gas compression, production and accommodation topsides. In addition, 36” trunkline, two 230KV subsea cables, and onshore scope for overhead transmission lines. Dodsal Group manages interfaces with several other contractors involved in the Marjan Increment Program.